Titan Shaves Eight Weeks Off Standard Lead Time for Blast Room Delivery
An industrial manufacturer located in the North East needed our 15’ W x 10’ H x 10’ L blast room package fabricated and shipped to them within four weeks.
While the size of the enclosure was standard, the company wanted the product doors located on the 15’ side versus the 10’ end.
This change meant our standard enclosure was now a custom job. Lead time for this type of job is 10 to 12 weeks, so meeting the four-week turnaround meant we had to scramble!
Design the custom enclosure
The customer requested 15’ W x 10’ H product doors be installed along the 15’ side of the enclosure to allow full access to the blast room (see Figure 1) – a relatively easy design change for our engineering department.
Once the drawing was approved by the customer, the enclosure was sent to production as a rush order.
6,000 CFM cartridge dust collector with photohelic gauge
Control panel
To meet the shortened time frame for the system components, we worked with our vendors – all of whom stepped up to help us meet the deadline (the benefit of years-long relationships based on trust).
System Installation
The customer wanted to handle the installation themselves. Normally we recommend having our factory installation team install systems to ensure everything is done to code, specification, etc. (See our Tech Tip, Preparing for a Blast Room Installation).
However, this particular blast room system wasn’t complicated, and we could tell from conversations that the customer was more than capable of installing the system.
As part of our service, and standard with all systems we deliver (no matter who does the installation), our engineering department provided exploded-view installation drawings and a recommended layout drawing for optimal performance. We also provided instruction manuals.
Ready to ship!
While the blast room enclosure was being fabricated, we built the various components of the system. In Figure 2, you can see the Titan dust collector and blast machine, plus various other pieces wrapped and ready to go.
We confirmed shipping logistics with one of our trucking partners. A flatbed tractor-trailer arrived on a weekday morning. The crated and wrapped pieces were carefully loaded onto the trailer, strapped down for the journey, and covered with a tarp for protection from the elements, road debris, etc.
The entire blast room system was delivered to the customer without mishap – meeting their four-week turnaround deadline.
We eliminate the middleman and sell direct to you
One reason we could meet this short lead time is because the customer was able to call us directly versus having to deal with a distributor before getting a quote.
The customer also worked directly with our engineering team to customize the blast room enclosure. Without a distributor in the middle, we could quickly answer questions and provide a drawing – as well as offer installation recommendations – without the associated miscommunications and delays.
This efficiency is one way we keep costs low and pass the savings – and shorter lead times – on to you.
Brandon Acker:President
Brandon purchased Titan Abrasive from his uncle and founder in 2013. Titan has since redesigned its entire product line to solve dozens of industry challenges.
Brandon purchased Titan Abrasive from his uncle and Titan founder, Bruce Maurer, in 2013 after spending five years learning the ins and outs of the business. He and VP of Engineering Brian Fox have completely redesigned the entire product line to solve the dozens of challenges that have plagued the blasting industry for decades.
Brandon is passionate about American manufacturing, the jobs it creates, the quality produced, and the bright future that lies ahead. He’s a frequent guest on manufacturing podcasts where he shares his deep industry expertise. Brandon holds a Bachelor of Science degree from Arizona State University.